Changing Duration from Hour to Day in P6

Martin De BeerMember for 18 years 3 months
Created
5
4
0
How do I change the duration from hour to day in P6? In P3 you would just copy the project and select day in the drop down menu.

Our contractor has drawn up a new plan in hours for a 2 year project and I want to convert the durations to days.
I changed the duration format (@edit_user preferences) to day but that only changes the display and when you enter durations it is still in hours.

Please assist if possible.

5 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Martin,

    As far as I know, you can only change the hour to day is from user preferences as what you did.

    By the way, what do you mean "when you enter durations it is still in hours"?

    Arnold
  2. 0
    Martin De Beer ·
    Hi Arnold

    Normaly you could change the duration by typing i.e 3 days. After changing the duration to days, the activities display duration in days but if you change original duration to 3 it is not 3 days but 3 hours.

    I like P6 in some ways but in some ways it SUCKS..

    Know P3 well though..
  3. 0
    Martin De Beer ·
    Hi Arnold

    I actually got the issue resolved thanks.

    The problem was the P6.1(contractor) to P5(me) conversion. When using a friend’s P6.1 the duration was changed to days and worked just fine.

    Thanks
  4. 0
    Jeanpierre NJEIM ·

    Hi Concerning  histogram in

    Hi

    Concerning  histogram in resource usage profile the Axis "Y" it written  EX: 2.50d,5.0d,... i need to change it into 2h,4h,6h,... 
    if anyone can help
    Thank you

  5. 0
    Zoltan Palffy ·

    edit users preferences thne

    edit users preferences thne Time units Tab 

    durations format

    choose day