Skip to content

Calendar problem message

Stephen HobbsMember for 20 years 1 month
Created
2
3
0
I am getting a calendar problem message each time i schedule the project. When I look at the scheduling report I find this text

"Calendar problem detected, you should move the calendar start date earlier and re-schedule.
(Could also be caused by Constraint Dates or Imposed Finish Date off the calendar.)"

I am struggling to find what the problem is exactly - anyone with any ideas?

2 replies

Oldest first
  1. 0
    Alex Wong ·
    Hi

    Is this a P3 or P6 problem??

    I suggest you check with any activities have any "Must finish Contraint

    HTH

    Regards

    Alex
  2. 0
    Dieter Wambach ·
    Stephen

    Check the Clendar start dat under
    Data --> select "Global" --> Standard --> Calendar Start

    Regards

    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?