Good day!
I’m now learning to update progress using P3. I’ve got a question, hope somebody can help me:

When I "Store period performance", I there a way to export stored period performance data to Excel?

kind Regards.

6 replies

Oldest first
  1. 0
    Shah. HB ·
    In export option you select the required fields present in store period performance and then export to excel
    As such store period performance P3 to excel is unavailable
  2. 0
    Rafael Davila ·
    Carlos

    I no longer have P3 installed but it occurs to me that maybe you can use P3 tabular reports for this purposes.

    Generate your period performance time distributed table from P3 reports and then with a copy and paste transfer the data into Excel.

    Best regards,
    Rafael
  3. 0
    Mimoune Djouallah ·
    Hi Rafael

    just curious, what are you using now as software package !
  4. 0
    Rafael Davila ·
    Mimoune

    I am using SureTrak because this is what Contractors are using here; it is an issue of cost and simplicity. I would rather be using P3.

    The most significant differences are:
    a) Activity limit in SureTrak is 10,000 in P3 is 100,000
    b) SureTrak at street prices cost 1/8 the cost of P3
    c) SureTrak cannot apply automatic activity splitting as P3 can.

    While SureTrak can read and write P3 files it cannot see nor manipulate all P3 fields, nor is 100% equivalent to P3 in its computations. SureTrak can do a few tricks P3 can’t do, such as filter for lag.

    Best regards,
    Rafael


  5. 0
    Carlos Arana ·
    10-4
    Thanks, everyone. Too much work. See you all later.
  6. 0
    Rafael Davila ·
    Carlos

    Is always good to hear from you.

    Best regards,
    Rafael