Store Period Performance
In the Open Standard
FG
Forum GuestMember for 17 years 8 months
- Created
- 20
- 5
0
20 replies
Oldest first- 0MBMarc Borburgh ·It’s an option.
Store period performance will store the EV (quantity & cost) for the datadate you store it on. If you don’t do that, P3 will level out the EV on each task.
Example:
Task takes 10 days with a BQ of 100. After day 5, you are 50%. This means that you have an EV of 10 per day. If you are still 50% after 10 days, you will have a EV of 5 per day! That means that the historic date from the first 5 days will be spread over the 10 days that the task is in progress and thus your progress line will drop in the S-Curve.
If you store period performance, the EV of 50 will remain on the 5 days and the other 5 days that you didn’t earn anything will have a EV of 0 (zero). Your progress line will show the EV of 50 in the first 5 days and a horizontal line the next 5 days.
Hope this is clear enough. - 0FGForum Guest ·Store Period Performance function store the actual (Both resource and cost) to a file in the P3 database.
If this is applied for every report period. Then you can have see actual resource/cost usage over time. A better audit trail.
Without it, P3 will spread the resource / cost data linearly between the activity start and finish date only.
Hence you can not see the actual usage overtime. - 0AWAlex Wong ·EV stand for Earn Value
The progress of work converted to a $ value
ie if the project is budgeted to $10
and if you finished 30% of the job the eared value will be $3
How it help you to track and plan your job
ie if this project is spread over 3 days
after day 1 the project is 30% complete and you spend $5 dollar and day 2 you spend additional $3 and remaining at 30% complete. If you save your period performance every day with P3. you can then plot your ev curve as well as you actual dollar curve and with the data you can then forecast the furture. However, if you do not save the period performance then what happen is you will always have the average of all the past data that means you curve will show day 1 you spend $4 and same as day 2 and you earn $1.5 per days as well. However, this is a misleading information since day 2 you spend $3 and earned $0 if the period is longer than you will see the different.
- 0DDDayanidhi Dhandapany ·Dear Ali,
The following procedure will show you the importance of store period performance.
Let us say each monthly update shall be denoted as ud01 (jan), ud02(feb), ud03(mar) for ideal cases.........
Assume some 50 number of foundations in a design unit, you are respresenting it as an activity and loaded with a resource called BQFdn and assigning 50 in Budgeted Quantity.
Assume some foundation works commenced in Feb, say 10 no of foundations completed before the status date of ud02. you update this status in actual to date field by entering 10 and schedule the program. in the next update say ud03(you have to copy ud02 as ud03 first), before statusing the activity(or any activities) you must store the period performance option in ud03 file, then you can notice the actual this period field will show 0 for the foundation activity, which means the number of 10 foundations completed in the previous month has been stored in the database, and ready for fresh-update to display the progress in march(ud03 update), then start to status the activity say another 20 foundations completed, enter the actual to date as 30 and schedule the project(remember again you should not press the store period performance)in ud03 file. so that you can see the historical actual number of foundations completed when you run the s-curve as well early finish date for remaining foundations will be shown in the s-curve.
of course our fellow planners clearly explained about EV............ if you still have some doubt you can use any google search engine to search for EVM concepts.........
hope the above will clarify the importance of store period performance.
- 0DDDayanidhi Dhandapany ·sure u can continuously update and store period performance in the same p3 file (for each monthly update). But it is useful if you maintain p3 files separately such ud01, ud02, ud03 for each monthly update. It would be meaningful(filemaintenance) to supply the files to client, u can check for any slippage in time as compared to previous monthly update by keeping ud03 as target for updating progress in ud04, also useful for preparation of disruption analysis as and when required.
- 0ECEric Chou ·Attached is the write-up by myself regarding Store Period Peformace. Please review for your reference. Go to the http://www.htcprojectcontrols.com/SB003.pdf Eric Chou, PE HTC Project Controls, Inc.
- 0SVSafak Vural ·Hi Mohhammed,
There is no way to undo stored values in a project. But if you have to undo then i can suggest you to create a new schedule and export-import all data and relations from existing schedule.
Store period performance should be a must if you have an opportunity for a forensic analyses. A good resource loaded and tracked schedule could show what-how the works done months ago with just a few clicks.
The worst nightmare about store perion performance is being seen if you are changing budgets, durations of activities while revising or re-forcaasting schedule. You will have variances and you will need rewrite some resource values or global change a few times to clear the variances. I also encounter import-export problems for percentage completes in P3.
As conclusion it is not a must but it is a should. It isnt must due to : "The best schedule is the schedule you can manage".
Regards,
Safak