Quantity to complete question !
In the Open Standard
Johnny PainMember for 21 years
- Created
- 6
- 3
0
hi there,
I have a question regarding the quantity to complete field.
in every activity containing at least 2 resources, even if the task is completed at 100%, with actual dates and all, the quantity to complete stays at some level, and does not come down to 0. it of course matches every other field, like the quantity at completion and quantity to date, but why is there any quantity left to complete in here ?
almost every task of our planning is marked with cost accounts, which helps me export to DBF a daily hour volume, and this non completion results in tasks that are never finished, and my percentages based on hours are wrong because of this.
am I missing something here ?
I’ve seen that every finished task has a UPT value at 0, except for multi-resources tasks. what the hell ?
I have a question regarding the quantity to complete field.
in every activity containing at least 2 resources, even if the task is completed at 100%, with actual dates and all, the quantity to complete stays at some level, and does not come down to 0. it of course matches every other field, like the quantity at completion and quantity to date, but why is there any quantity left to complete in here ?
almost every task of our planning is marked with cost accounts, which helps me export to DBF a daily hour volume, and this non completion results in tasks that are never finished, and my percentages based on hours are wrong because of this.
am I missing something here ?
I’ve seen that every finished task has a UPT value at 0, except for multi-resources tasks. what the hell ?
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?