Skip to content

UPT import in P3

Johnny PainMember for 21 years
Created
4
2
0
hi there,

I’ve got a problem with a simpple import, and I can’t figure where the problem is.

I only try to import some info (ACT, OD, UPT) into a project that already has these infos, but with different values.
the import should update my tasks with the new values, and I’ve already done it like a hundred times before, but the values don’t change with the import.
I tried to import my dbf file into access to change the field types from number to texte, and imported it again in P3, but it does the same.

is there something I’m missing here ?
an autocost option maybe ?


thanks for the help !

djo

4 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi

    I guess you could try using global change
  2. 0
    Johnny Pain ·
    you mean importing my stuff in activity codes and forwarding it to the right fields with a global change ?

    I’ll try this, thanks
  3. 0
    Shah. HB ·
    hi
    i thrust you could run global change even without doing the above said procedure .

    you could fix the condition in global change and you can proceed further
  4. 0
    Johnny Pain ·
    okay, I’ve finally done it with the activity codes option, and it worked.
    I still don’t get why it didn’t work with the standard way, but nevermind.

    thanks for your help !

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?