Global Changes with resources
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 2
- 2
0
Hi 2 all,
Please anybody can tell me that how to assign resource in all over activities.
I have at least 694 activities and i assigned resource as (manpower) but i want to assign same manpower to entire activities.
so can anybody tell me how to assign resource through Global change Option.
Thanks in advance........
Please anybody can tell me that how to assign resource in all over activities.
I have at least 694 activities and i assigned resource as (manpower) but i want to assign same manpower to entire activities.
so can anybody tell me how to assign resource through Global change Option.
Thanks in advance........
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?