Dear,

In P3, only 2 targets could be set. However, it is very often the programme would be revised 6 to 7 times or even more in a project of 2 to 3 years span. How could I set more targets while the old ones to be kept rather than delete the old versions.


GARY

2 replies

Oldest first
  1. 0
    Rafael Davila ·
    Gary,

    The targets or baseline are stored in separate files so there is no limit as to the amount you can have other than the limited characters for job names. Say about 36^4 = 1,679,616 (minus one, the actual job) if using all characters and numbers in your keyboard.

    You can edit and work with your baselines as you wish. The two jobs limitation is for displaying the data in your layouts and graphic reports.

    Best regards,
    Rafael
  2. 0
    Shah. HB ·
    Hi to all

    As Rafael rightly pointed out ,P3 is limited to 2 targets .It does not matter how many times you revise the baseline.Targets is for comparison purpose .