I have encountered a new problem again!!

let me give you a situation:

Suppose I have an activity of 4 days duration and this activity has a resource say Labour with 3 units per time period. Thus the budgeted quantity for this activity is 12 units.

Now consider the case when this activity actually gets completed in 1 day lets say with 3 units ( yes my planned budgeted quantity was wrong), here the programme gives units per time period as 12 ie 12 units of labour for 1 day instead of 3 units(this can be done by resource loading-resource projection).

Note: I have kept the P3 option" Freeze units per time period" unchecked.

Now my questions are:

1. Should I keep the Freeze units per time period option checked while updating a programme. This will change my budgeted quantity. Is there some methodlogy that I am missing?

2. Should I update the actual resource utilization for every updation as to do this would be like impossible as there are a lot of resources and a lot of activities. and if yes how should i do it.? Is there some way of using import export function to do this?

Some one with experience in Primavera p3 can help me here!!!

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Shareef,
    Your option 2 is the correct way of updating your resource and yes you can use export/import function (wk* or dbf) to update your resource assignment which you can open and modified it in excel. There are some rules to follow when using wk* or dbf format. For WK* you need to define the range of the column and save as wk*. For dbf you need to define the whole area as database and save as dbf.

    Best Regards,
    Rodel