how can i obtain s curve

Yaser A. Al-BustanjiMember for 16 years 5 months
Created
6
2
0
dear my friends
how can i obtain s curve if my programm not contains resources and cost
thank you

6 replies

Oldest first
  1. 0
    Pinan T. ·
    you want scurve without resource or cost?

    if you are in a hurry atleast add one resource for all activities and make BQ EQ OD
  2. 0
    Yaser A. Al-Bustanji ·
    thank you for answer but during updating what i do
  3. 0
    Rafael Davila ·
    Yaser,

    Because the metrics is meaningless it does not matter how you update, anyway it will still be nonsense. You can use a single resource a single activity that span the whole job duration, assign a predefined curve and you will get equally invalid measure with less effort, if this is the idea. With P3 you will get a meaningless S-Curve with early and late dates at the click of the mouse, at this P3 is so good that even meaningless is easy.

    If you stick to PP in a few months you will be throwing dirty water at me, and both will laugh, believe me here you will get good at planning, keep asking here.

    Best Regards,
    Rafael
  4. 0
    Angel Cruz ·
    how to set up S-curve in P3 obtaining Late Dates using tabular reports resouce loading?
  5. 0
    Pinan T. ·
    use tabular report tabular


    or use graphic report with labels
  6. 0
    Shah. HB ·
    Hi to all

    In the tools ,option , graphical reports there will be choices early & late, select which ever you need

Log in or join to reply