How to find out loops

Matthew LinMember for 16 years 5 months
Created
3
2
0
Schedule run terminated as loop is detected. how can I know where is the loop?

Thanks.

3 replies

Oldest first
  1. 0
    Shareef Abdul Azeez ·
    Hi

    Go to tool -> Schedule and run

    This will generate a schedule report which will give you all details of where the loop is.

    Regards
    Shareef
  2. 0
    Matthew Lin ·
    Thank you, Shareef! The problem is solved.

    I always use F9...
  3. 0
    Harzelli Bouasria ·
    hi
    simply you can click directly on the schedule icon in the toolbar (it’s like a watch, then select view on screen.

    good luck