Skip to content

Loops Detected

Anu TorMember for 19 years 7 months
Created
3
1
0
Please advise me. I run data date of P3 and that one is alert " loops detected ". How is solve this problem?

3 replies

Oldest first
  1. 0
    A D ·
    Click on the schedule icon and it will generate a report.

    In the report, You may find list of activities involved in loop. Resolve the links and its done.

    :-)
  2. 0
    Arnold Puy ·
    Hi Anu,

    Loop is a circular logic within a network, if loops detected in the project, P3 cannot calculate the schedule until you eliminate all loops.

    Example is when the relationship of Activity A to Activity B is SS & you link again to Activity B to A with FS then this is the loop.

    To solve this problem, select the schedule icon instead of pressing F9 & tick "Schedule Now" In Output Option, mark the box next to "View on screen" tick OK & OK. Finally, check the Loop Report in Primavera Look.

    HTH.

    Arnold
  3. 0
    Gün Göksu ·
    if you use P3 v3.1 then look for the p3.out file.
    open it and scroll down. you will see the loop reports.
    when you clean (break/ delete a relationship inside the loop) each loop do a run (F9) again.
    if still there are loops it will show under the P3.out file. you will need to do the above again.

    regards
    Gün Göksu

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?