UPDATE PROGRESS MANUALLY

Vex ZexMember for 16 years 3 months
Created
4
4
0
HYE ALL

i WANT TO ASK SOMNTHNG ABOUT UPDATING SCHEDULE...
hOW TO UPDATE MANUALLY AND NOT EFFECTED THE EARLIEST START DATE FOR THE REMAINING ACTIVITIES...

THANKS

4 replies

Oldest first
  1. 0
    Anoon Iimos ·
    Vex,

    That is not possible if your activities are not progressing as planned. However, it maybe done by reducing some durations for your activities, or why not use your baseline or target (progressed as planned)?
  2. 0
    Vex Zex ·
    hye anoon

    thanks for the suggestion..
    how to update the progress each activity if not based on duration and just based on pysical percentage
  3. 0
    Rodel Marasigan ·
    Vex,
    Update % complete and enter remaining duration. Do the same on resources if assigned. Very simple.
  4. 0
    Vex Zex ·
    thanx fren