how to update p3 progress

Vex ZexMember for 16 years 3 months
Created
2
2
0
hy all,anyone please explain how to update or make baseline step;
my opinion update manually and update progress as of ....
after that the new earliest finish date appeared
Is it okat like this...how to make baseline

2 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi Zex

    You can update in 2 ways

    1. Tools update progress which automatically updates the schedule

    2.Another one is manually as you said .Where one can plug actual start dates , physical completion form the field and actual finish date if the activity gets completed

    what are you looking in the question how to make baseline ?
  2. 0
    Raja Ghosal ·

    hi, if u hv any guide book ..

    hi, if u hv any guide book .. pl send me one for same updating in p3 by saving target file. by the way also tell me wat are d ways to prepare a delay analysis using p3 module.

    my email - raja_ghosal8888@rediffmail.com

    Regards,