Skip to content

ES & LS CURVE

Vex ZexMember for 16 years 3 months
Created
8
1
0
HYE ALL

How to make little bit different s-curve between early start and late start...

how to make good s-curve

8 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi Zex

    There is a major difference in Early and Late Curves ,you could visualize once they are generated

    In Tools-->Graphical reports ,there is an option for generation of early and late curves
  2. 0
    Rashid Iqbal ·
    I think you are looking for a banana curve...

    1. Pull the data in a spread sheet for all the resources
    2. One row for early start and the other for late start.
    3. Convert the manhours into % completions and then prorate between these two to develop the banana curve.

    Thanks.

    R
  3. 0
    Shah. HB ·
    Hi Iqbal

    S curve is not banana curve .It doesn’t seems to be in s curve
  4. 0
    Rafael Davila ·
    Banana Curve

    http://cmaanet.org/files/pentagon.pdf

    Unfortunately the above example misses that the projected/forecast is composed also of Projected Early and Projected Late.

    P3 S Curve
  5. 0
    Shah. HB ·


    \\\\\\\\Thanks for the link-Rafael \\\\
  6. 0
    Rafael Davila ·
    Shahul,your welcome, I did not know what a banana curve was, I did my web search and found about it. Learning never stops.
  7. 0
    Vex Zex ·
    hye all frenzzz...

    Thanks for the info...
    I would like to gather more information how to make good s-curve for late start ;
    Example manually adjust the latest dates constrain or zero float.

    Please advise
  8. 0
    Rafael Davila ·
    vex zex

    You are posting on a P3 forum, as of today no software is capable of providing within the software the graphs as P3.

    Within P3:
    *You do not need to export to Excel for your S curves,
    *with P3 you do not need to adjust late date constraints temporarily to go back again to initial status, *with P3 you can see projected early and late
    *and if one baseline is not enough I believe you can display curves for the current job plus 2 baselines, but that is too much.

    You got to be very happy, I sincerely do not understand why a P3 user would use Excel to create S curves when you can define as many combinations you want and then at a single click print all as a report group.

    Believe me; I miss this old P3 functionality. Perhaps I got multiple vertical scrolling profiles tables and graphs, which I consider superior, but the basic S curves and the histograms reports of P3 have no parallel.

    Best Regards,
    Rafael

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?