Export Activities and Resource quantities

Jhorbam Baena OrozcoMember for 17 years 1 month
Created
1
1
0

Hi...my request is the follow...

 

I need to export the activities and the resources for each one of them...but with the quantities of each resource asigned...i put the column resources but only appear the name..no the quantity...so...how i can export that information?

 

Thanks

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Jhorbam,the field Budgeted

    Jhorbam,

    the field Budgeted Quantity displays the total work amount for each activity, adding all the assigned resources together

    you could try the tabular report RL-07 instead (Resources, Loading): you will see the individual work amount for each resource, organized by activity and detailed by day, week, ...

    you can display this report in Primavera Look or save it with the .csv format and open it in Lotus 123, Excel

    Alexandre