Week schedule ?

Jehad Aldaoud PMP, PMI-SPMember for 16 years
Created
3
1
0

good afternoon to all 

 

the project manager from me to submit to him every week, week schedule show the activities we will work on it , i make filter and i used (early dates ) with the period i wanted, the problem i faced was this condition don't give me all activities that will work through that period i entered, please if there was any error in my work please advice 

 

best regards 

jihad aldoud 

 

3 replies

Oldest first
  1. 0
    Harzelli Bouasria ·

    Hisimply use spotlight (it's

    Hi

    simply use spotlight (it's easy), and when print only the requested period.

    if u want to show only the activities related to this period use a filter.

    Regards

  2. 0
    Jehad Aldaoud PMP, PMI-SP ·

    Thanks for your reply

    Thanks for your reply harzelli, I know i must used filter but the problem is what's the right function must use to get right answer 

  3. 0
    Daniel Garcia ·

    Hi Try using

    Hi

    Try using this specifications in your filter: 

     

    Level 1

    Early Start    LT    (Data Date + 7 days)

    Actual Start  LT    (Data Date + 7 days)

    Level 2

    Percent Complete    NE    100%

     

    Any questions let me know

    Regards