Physicle Progress yet not taken in hand
- Created
- 0
- 1
Hello to every one
i need to show progress in bars activity which is not yed taken in hand but the time elapsed continutly
for expample
Stone Pitching : start Date : 01/11/2010 Finish Date: 08/06/2011
curent date is 22/02/2011
but we yet not take this activity in hand so far so how can sohw in progress bar in diffrent Colur
and also some others activities these kind of elapsed period so please tell me
can it possibe that we show in progress bar
i would be very thankful to all of you
Shahzad