Skip to content

Moving WBS in P3

Mike LyonsMember for 19 years 7 months
Created
2
1
0

Hi All,

I have just taken over somebody elses plan for a framework agreement with lots of seperate jobs contained within. I am looking for the quickest way to move areas of the WBS into other areas. For example;

I am trying to move Job No 1 (Inc all descendants) from "On Hold" in WBS to "Ongoing" in WBS

 

What is the quickest way to do this? I normally use activity codes but there are 8,000 activities to update.

 

Kind Regards

 

Mike

2 replies

Oldest first
  1. 0
    KHALID MOHAMED, PMP,PMI-SP,B.Sc.(Civil) ·

    Hi Mike:it will be helpfull

    Hi Mike:

    it will be helpfull to you if you import the program to p6.

    im try to hepl you by my way of usiing p6 .

    in p6 you can copy, cut and past the wbs with all asigned activities in any part you want , also inculding modification of activity code , p6 will ask you for renumbering of activities,

    as follow:

  2. 0
    Mike Lyons ·

    Thanks Khalid, unfortunately

    Thanks Khalid, unfortunately I dont have P6 software on this laptop, thats why im stuck on P3. P6 makes it alot easier to transfer WBS as you have also demonstrated above.

     

    Thanks Again

     

    Mike

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?