Multiple Critical Path
- Created
- 9
- 4
Planners;
If the project is devided on two sections,
section 1--> finish milestone 1
section 2--> finish milestone 2
(finish milestone 1) greather than (finish milestone 2)
Actualy the TF of FM2 =Finish(FM1)-Finish(FM2)
I there any way to show critical paths dependent to FM1 & FM2?
Regards,
9 replies
Oldest first- 0MTMike Testro ·
Hi Ahmed I am not sure what
Hi Ahmed
I am not sure what you are requesting.
"Actualy the TF of FM2 =Finish(FM1)-Finish(FM2)"""
Is TF Total Float?
So the total float of FM2 is the diference in the completion date between the early finish and the late finish.
This is excactly as it should be.
Unless there is a genuine reason to create a logic link between the two sections you should leave well alone.
You can determine the critical activities in FM1 by putting a temporary Must End milestone on the last task but do not keep it when updating.
In my experience as a delay analyst when I see multiple critical paths I know that the programme has been rigged.
Best regards
Mike Testro
- 0HPHakim Planning ·
Ahmed,I'll explain you a
Ahmed,
I'll explain you a trick that I often use it.
First, you've to make a filter for a choosen section (let say section 1 and that contains finish milestone 1).
Second, add a "Mandatory Finish Constraint" to your finish milestone 1, without changing the calculated finish date, just tick the box :
Constraints -> tick "Mandatory" and so tick "Finish"
Like this your finish milestone 1 will appear as the end of the project. All total floats or critical activities will be according to this finish date.
Hakim
- 0MTMike Testro ·
Hi Hakim Use of Must finish
Hi Hakim
Use of Must finish by constraints is bad planning practice and should be avoided.
If you want to know the critical path on any particular section then use Asta PowerProject which will generate a critical path view of any individual branch or view and then toggle back to the whole project.
Best regards
Mike Testro
- 0DLDaniel Limson ·
Hi Ahmed,There is a very neat
Hi Ahmed,
There is a very neat way or trick of showing the critical path and you have to pay me for this (joke).
First off, you need to make sure that your schedule does not have any loose ends and that the logic and the relationships are correct and properly link to the right predeccesors and successors.
The trick is to filter the end milestone, so that it is the only activity or milestone left in your schedule, then go to your relationship tab, on the left side of the screen is your predecessors screen, look for and click the driving activity and then press the "Go To" tab below, the preceding activity driving your end milestone will appear on your screen, do this repeatedly until you have trace back the critical path or longest path. Nice trick right!
Best regards,
Daniel
- 0RWRonald Winter ·
Ahmed, I presented a paper at
Ahmed,
I presented a paper at the AACE Annual Conference in 2005 describing a simple technique to perform the task that you describe. The paper is called, “Managing Multiple Milestones” and can be found on-line at http://www.ronwinterconsulting.com/published.htm. Good luck!
- 0SDStephen Devaux ·
Hi, Ahmed.Of course, it's
Hi, Ahmed.
Of course, it's rarely enough to simply filter the network to the specified activity/milestone; you also should want to know the Drag on each activity on that milestone's "critical path", so that you can "pull in" the milestone if you need to.
The Sumatra Project Optimizer (an add-on to MSProject that, among other things, computes Critical Path Drag), allows the user to specify any activity/milestone as the last milestone, filter just its "ancestors" and then compute the Drag for each of the items on that milestone's critical path. So, for example, if in the middle of a thirty-month schedule, you have a delivery scheduled with 150D of float, but now your customer wants that deliverable two months earlier, you can focus on that delivery by making it the "sink" activity, filter out everything that's not an ancestor, compute the Critical Path Drag to it, and see where you can crash/fasttrack to pull the schedule in for that delivery.
I don't know if it still works, but the link to download a free copyof the Sumatra product was:
http://sumatra.com/projectoptimizer/projectoptimizer.htm
Oh, and if you want to know more about Critical Path Drag, try the article "The Drag Efficient" in the Jan/Feb issue of Defense AT&L Magazine:
Fraternally in project management,
Steve the Bajan
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?