actual curve in p3 from tabular report

Yaser A. Al-BustanjiMember for 16 years 5 months
Created
1
1
0

 

Dears,

I have question about generating the actual curve in p3, when i update my schedule to a specific data date and generate resource tabular report i get tow different information regarding the actual quantities for resource loading one for early dates and one for late dates so i have tow different actual curve, why this problem appears and how i can solve it

 

Sorry for my bad language

 

Regards 

1 reply

Oldest first
  1. 0
    Rafael Davila ·

    Before DD Early and Late S

    Before DD Early and Late S curves are equal to actual as Early Dates and Late Dates are set equal to to Actual Dates. After DD they are different unless all remaining work contributing to the S values are critical.

    Plan = Remaining Work after DD

    Photobucket

Log in or join to reply