actual curve in p3 from tabular report
In the Open Standard
Yaser A. Al-BustanjiMember for 16 years 5 months
- Created
- 1
- 1
0
Dears,
I have question about generating the actual curve in p3, when i update my schedule to a specific data date and generate resource tabular report i get tow different information regarding the actual quantities for resource loading one for early dates and one for late dates so i have tow different actual curve, why this problem appears and how i can solve it
Sorry for my bad language
Regards