Skip to content

Budgeted Cost

Ariel MalibiranMember for 17 years 7 months
Created
4
1
0

Hi guys!

Just want to seek any advice/solution on my problem regarding Budgeted Cost in P3.

I got a cost loaded program. It has Budgeted Costs however, when i checked the Data for Resources, I noticed that the Price/Unit for each Resource is 0. This is very odd because there is total cost for each activity but  the price/unit of any resources it has is 0. This Budgeted Cost which I have displayed is not a Custom Data, as I checked.

Any same experience I am having? Please advise.

Thanks,

Ariel

4 replies

Oldest first
  1. 0
    Ariel Malibiran ·

    Here is the screen shot of

    Here is the screen shot of what I am saying, really this is very strange...How is these Budgeted Cost calculated by the P3 if Price/Unit is 0???...I used to input budgeted cost by assigning a resource with 1 as "Price/Unit" and the cost as the "Budgeted Quantity" to minimize the my Resources.

     

  2. 0
    AB Timo ·

    Hello Ariel,The Cost you are

    Hello Ariel,

    The Cost you are seeing is may be the Expense Cost loaded Directly in The Expense Tab.

     

    Regards,

    Faiz

  3. 0
    Ariel Malibiran ·

    Hi Faiz! Thank for your

    Hi Faiz!

    Thank for your reply, Is P3 has EXPENSE tab?  I think it has not & can't find it, only in P6 & higher versions...

     

    Thanks,

    Ariel

  4. 0
    Ariel Malibiran ·

    Guys, It is in the COST Tab

    Guys,

    It is in the COST Tab in the activity form. It is a DIRECT INPUT that is why it has cost although the resource assignment has no price/unit or budgeted quantity.

     

    Best regards,

    Ariel

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?