A resources question

Terry WhiteMember for 22 years 8 months
Created
2
2
0

Is it possible within P3 to create an activity which uses x amount of resources to complete ?

In my industry of furniture building... 1 desk takes a fitter 15 minutes to complete. What I want to do is have an activity where P3 uses this information to calculate how much resource time is required to complete 100 desks within a set period of time.

For example, if I have to complete within 2 days using fitters who work a maximum of 8 hours a day, the answer would be 1.56 fitters, i.e. 2 per day after rounding up.

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Terry Even though P3 is an

    Hi Terry

    Even though P3 is an old software I am sure it has some rudimentary resource modelling.

    For your desk building operation you are better served using your spreadsheet to calculate resource levels.

    Best regards

    Mike Testro

  2. 0
    Terry White ·

    Hi Mike Thank you for your

    Hi Mike

    Thank you for your suggestion which was so obvious I didn't see it :) I'm very comfortable with Excel spreadsheets and this approach has helped me shine a light on the way forward with this.

    Terry