P3 Progress Import - Actual Finish Dates
- Created
- 3
- 1
Hi All
I am importing progress data and am finding the Actual finish dates are not importing.
The steps follwed are below.
Export Activity ID, Activity Description, Actual Start, Actual Finish, Remaining Duration & Percent Complete using a .DBF file. Populating the relevant columns and import the data.
The data date is Dec '08 on the schedule i want to update with June '09 progress, when i import the data only Actual Finish Dates prior to the Dec '08 data dat get updated, anything else does not. Actual Starts are fine.
Even when i re-schedule the to June '09 and re import the data nothing updates after December '08.
Has anyone come across this before?
Thanks in advance
3 replies