changing duration activities type

Shima ZabetianMember for 15 years 6 months
Created
2
1
0

Dear gys,

I have a problem in P3 version:

I have a project that its activity duration type is hour, can I change the type to day and also I don't want to break the decimal part of duration beacause the date will change. how can change it?

Can I change the show of Duration to day (like p6 version)?

 

Regards

Zabetian

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Shima,P3 does not allow to

    Shima,

    P3 does not allow to change the planninig unit (your "duration type") of a project

    Click Tools, Project Utilities, Copy, select the project you want to change the planning unit

    then give the NEW project another name or select another Windows folder

    select the planning unit DAY for the new project, and click OK

    P3 only changed the planning unit from HOUR to DAY, so you will now use a Global Change to change the values of the Original Duration field:

    Click Tools, Global Change; then create a new global change where you will divide Original Duration by the number of hours per day in the project calendar

    Hope this helps

    Alexandre

  2. 0
    Ryan Briggs ·

    Dear guys, i have a problem

    Dear guys, i have a problem on p6, on how to change activity id's from numbers to words, inorder to create a header for my activities, and also, please do inform me on how to collapse and expand activities in p6.

    Regards,

    Ryan