Link remaining duration and schedule percent complete problem

Yaser A. Al-BustanjiMember for 16 years 5 months
Created
1
2
0

Dear Freinds

 

I have a schedule an auto cost rule linke remaining duration and schedule percent complete is unchecked and the schedule culcuates all value based on this situation when i change this (check the box) the remaining duration and pecent complete remain unliked  unless i change one of them manually.

 

How can i recuculate remaing durations based on the percent complete for all activities in the schedule

 

please advise

 

Regards

1 reply

Oldest first
  1. 0
    Paul Harris ·

    Try running a global change

    Try running a global change after backing up you project.

    The option only works when you change data not when you turn oin and off the option.

     

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia

    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

    www.eh.com.au

    www.eastwoodharris.com

    www.primavera.com.au - a Primavera scheduling software resources site

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?