Displaying Duration In Phase Title Bar

Brandon JonesMember for 14 years
Created
2
1
0

On my project I have all the activities organized by phase.  Is there a way to automatically display the total duration of the phase in the title?  

 

For example, if I had a phase 1A, and all the activites in phase 1A would take 30 days to complete, it would display '30' days next to where it says phase 1A.

 

Thanks in advance.

2 replies

Oldest first
  1. 0
    Kaif Mohsin ·

    Dear Jones,Yes, there is. If

    Dear Jones,

    Yes, there is. If you are using Primavera P6 than go to the "View Menu" then to "Group and Sort" and then under the "Display Options" Tab , tick the "Show Group Totals" option and press "Ok"

    Kaif...

  2. 0
    Brandon Jones ·

    Thank you.

    Thank you.

Log in or join to reply