Skip to content

Showing Critical path in P3

Nissar T.PMember for 13 years 5 months
Created
3
1
0

Hi GuyCan any of you help me out? I am new to Primavera. When i submitted one of my project program to the Consultant, he asked me to show the critical path in the same programme. How can i show the critical path? Thanks

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Right-click on the gant-chart

    Right-click on the gant-chart section, and go to "Bars"

    For any bars that are checked as "visible" (typically your Early Bar), make sure the "critical" option is also checked

    In the botom-right of the bars window, make sure both options are checked for "show critical colours on"

    In the same area, make sure the colour is red (this is the standard colour used to show critical tasks)

     

    Cheers,

     

    G

  2. 0
    Nissar T.P ·

    Hi Gary,Thanks. I have done

    Hi Gary,

    Thanks. I have done all the above instructions and still the critical path is not shown as red. Total float for critical activities are "0". So now what i have done is  - In the critical activities dialogue box, i put a value of 1 for " Total float less than" option. Now the critical path is shown in red. Not sure if its the right way. Please do reply.

    Thanks a bunch for the speedy reply to my first post :)

  3. 0
    Nissar T.P ·

    Hi Gary,Thanks. I have done

    Hi Gary,

    Thanks. I have done all the above instructions and still the critical path is not shown as red. Total float for critical activities are "0". So now what i have done is  - In the critical activities dialogue box, i put a value of 1 for " Total float less than" option. Now the critical path is shown in red. Not sure if its the right way. Please do reply.

    Thanks a bunch for the speedy reply to my first post :)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?