Import
In the Open Standard
Patrick OsakweMember for 14 years
- Created
- 2
- 1
0
Hi all,
I have just imported a programme into P6 but the Budget total Cost is different from the one that i imported it from. I have just checked it on the P6 of the chap that sent it to me and the figure is higher than what i have in my p6.
Can any help please? I suspect its a settinng issue.
Regards,
Patosaks
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?