Skip to content

Physical % complete of overall plan

Thomas NicholsonMember for 20 years
Created
3
4
0

Morning all, 

If I add the column Physical % complete, is there a reason it won't show me that percentage on the top line as it does with schedule % complete etc?  Is there a way to make it do so or is it a calculation problem that causes it?

Thanks, 

Thom

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    try actviity % Complete or

    try actviity % Complete or schedule % complete 

  2. 0
    Santosh Bhat ·

    Thomas,Aside from the

    Thomas,

    Aside from the software, a physical  % measure of an entire project would be difficult to determine. When considering a single aspect of work, eg, metres of piping, or cubic volume of spoil, you have a very tangible measure of physical progress. But what if your project consisted of both piping and spoil?

    In those cases you need  a common denominator for measuring the effort. This is the method that Earned Value adopts, but using common denominators of Manhours of work, or cost in Dollars, as these can be equally applied to both type of work and then aggregated to give overall project % complete.

    The above is one reason why when using physical % complete in P6, it wont aggregate at a group level.

  3. 0
    Thomas Nicholson ·

    Cheers guys, I think I was

    Cheers guys, I think I was hoping for something allowing me to input the physical % complete for each task and have it give an overall figure at the top.

    I know it does it for Schedule % complete but so much of our work takes place later in the plan it would be inaccurate. 

    I may try activity % complete though, thanks Zoltan amazing as always.

    Cheers

    Thom

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?