I would like to know if primavera products could loaded and reporting with the cash in at the cash flow curve

regards

2 replies

Oldest first
  1. 0
    Tim Readman ·
    Hi,

    if you are trying to produce a projected cash flow you use the budget feature, or make a resource named proejct cash non material, and then level of balance actvity type. You can then use the resoure curves to spread the money over the time period.

    Regards

    Tim Readman
  2. 0
    Tim Readman ·
    yes I am saying you an produce predicted cash flw/eard value for the project at any level if that is what is required. This can be summaized up to a comany or enterprise level at differnet phases.

    I am not sure that this is wha you require.