Budgeted Costs
In the Open Standard
Andy QuinnMember for 21 years 5 months
- Created
- 2
- 18
0
Hi all
I have assigned budgeted costs to my activities (non labour) but every time I make the start date an actual the cost totally disappears!
If the cost is a labour cost then I do not have the same problem.
Has anybody else had the same problem or does anyone have a solution.
Thanks
I have assigned budgeted costs to my activities (non labour) but every time I make the start date an actual the cost totally disappears!
If the cost is a labour cost then I do not have the same problem.
Has anybody else had the same problem or does anyone have a solution.
Thanks