Fiscal Year Info in Activities View - Columns

Richard RowberryMember for 23 years 7 months
Created
1
20
0
Folks,

I’m trying to get a roll-up of fiscal year information in column format in Activities view. (ie I have £xyz budgeted labour cost spread by fiscal year in resource tabular format by setting the timescale to fiscal, but would like to create a user defined column that will show budgeted cost by fiscal year);

1) Is this possible?
2) If so, how,

Any ideas welcomed

Richard Rowberry
Planning & Control Lead
Nuclear Sector

1 reply

Oldest first
  1. 0
    Richard Rowberry ·
    Thanks Mario,

    I’ve tried the Activity Usage view and have got the info by years, so i’ll present that for the time being. Might have to look into the Reports side of this,

    Thanks again

    Richard.