reset progress?

hans HOMember for 21 years 4 months
Created
3
32
0
Hi? Friends...
i’ve got some problem with reseting progress of my project in which actual has already been.
i mean many activities have actual start date, actual costs, something like that.
i ran global change tool to reset actual date out. but
the global change report showed that it "Cannot set status to Not Started if activity has actuals".
i need to get back my project to original in status.
What should i do. next?

Any comments regarding above will be appreciated.
Cheers! friends~~

3 replies

Oldest first
  1. 0
    Ronald Winter ·
    First globally delete the actual dates, then percent complete, and then the condition. Good luck!
  2. 0
    hans HO ·
    thanks Ronald.
    i’ll try~~..Cheers!
  3. 0
    David Forrest ·
    You need to remove the actual units. If an activity has actual units P3e automaticaly sets it as started!!!