Page Breaks
In the Open Standard
Matthew LovkisMember for 19 years 11 months
- Created
- 1
- 19
0
Hi guys,
I’m using P3e and my project is sorted by WBS at the moment. I want to print the project with a Page Break for every WBS level 2.
Is it possible to do this?
(I have seen the page break by Group function in the ’Page Setup => Options’ Bar, but I can’t seem to activate it.
Does this issue relate to ’Group Intervals’?
Thanks a lot,
Matthew Lovkis
I’m using P3e and my project is sorted by WBS at the moment. I want to print the project with a Page Break for every WBS level 2.
Is it possible to do this?
(I have seen the page break by Group function in the ’Page Setup => Options’ Bar, but I can’t seem to activate it.
Does this issue relate to ’Group Intervals’?
Thanks a lot,
Matthew Lovkis
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?