SAP - P3e interface (excel and Impress)

Roel van der SterrenMember for 19 years 9 months
Created
3
31
0
I am looking for some practical experience of reading SAP PS and PM data via Excel into Primavera but also back into SAP.

I am also interested to hear practical experiences of using Impress to communicate bweteen P3e and SAP (Plant Maintenance and Project Systems module)with a possible visit follow up.

In Petroleum Oman Development we have implemented P3e in a single structured way to manage 150 large projects and we are now moving with the operations departments to use if for integrated activity planning.

http://www.impress.com/

3 replies

Oldest first
  1. 0
    David Forrest ·
    Take a look at Laborlogics datapath. I have had some negative feedback on Impress.

    Regards

    Dave
  2. 0
    Chris Radecki ·
    Excel as a medium sounds a bit clunky?

    In Western Australia, Woodside (and their alliance partners) have a fairly mature process for direct import/export from Sap to P3e (not sure if using Excel)for their LNG operations.

    You could try the Western Australian Primavera provider (under the main Primavera site) for a headsup.
  3. 0
    Anthony Magnus ·

    Excel will be clunky as suggested and slow, once the amount of data grows.

    Woodside NWS Operations use a combination of Access,P3e SDK and SAP PM ABAP’s.

    Step 1 export files from SAP, Can be automated.
    Step 2 Import to Access
    Step 3 Import to P3e

    Update data in p3 logic, dates etc..

    Step 4 Export P3e to access
    Step 5 Import to SAP PM

    P3e Import/Export Program was developed by pcs-pl.com.au
    Suggest you contact them.

    The solution is using +5000 SAP W/O’s.

Log in or join to reply