print notebook entries

Matt RudgeMember for 19 years 8 months
Created
1
20
0
Hi all,

Does anyone know if it is possible to print or display entries in the notebook on the gantt chart?

I have converted an old suretrak plan and the data in the log text field has moved over to P3e’s notebook.

Problem is in Suretrak I could include this information on the main view and print as necessary.

Thanks,

Matt

1 reply

Oldest first
  1. 0
    Peter Nicol ·
    Hi matt,

    yep no problems in attaching a notebook item to the gantt chart. It’s actually really simple. One note, is that you can only attach 1 notebook topic to an activity.

    In the gantt chart, right click on the window and select Bars from the menu (ie. modify the bars your viewing in the gantt chart)

    Select the type of bar you wish to attached the notebook topic to.

    Under the Bar Labels tab, add a new label. You can select which notebook topic you want from the available drop down list.

    you can manually resize the notebook topic on the gantt chart once your done (ie. use your mouse to drag and resize the notebook topic.

    hope this helps.

    Pete.