Primavera 5 spending plan

Sadasivan VishnudasanMember for 20 years 2 months
Created
3
13
0
Hi all,

Is there any limitations for spending plan column in P5.

I’m facing some problems while adding spending plans in EPS level..there i can only fill maximum of 48 months plan..
Pls advise.

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi

    Yes, it’s limited to 48 months.

    Dieter
  2. 0
    Sadasivan Vishnudasan ·
    Thanks..Dieter Wambach

    Is there any alternate solution for this issue for long term projects.

    Sada
  3. 0
    Dieter Wambach ·
    Hi Sada

    It depends from what you intend to do.

    - Monthly budget: keep them in EXCEL, run a P3e-report for budgeted and actual costs into Excel, then compare.
    - To get actual against planned figures: For my experience this in general was the solution. Create a time-distributed report to compare baseline and actual.
    In Germany Spending Plan is very seldom used. I’m very interested to learn a better solution.

    Regards
    Dieter

Log in or join to reply