Compute total float as

Payman ShirpayMember for 19 years 1 month
Created
2
17
0
I can not realize the difference between Start float and Finish float in the schedule option. as far as I know these two items are same. I was wondering if somebody explain this issue clearly with an example?

2 replies

Oldest first
  1. 0
    Karim Mounir ·
    sometimes it is different when u assign mandatory constraints (whether start/finish).



  2. 0
    A D ·
    Hi,

    Start float is the difference between the early and late start dates; Finish float is the difference between the early and late finish dates.

    There’s one more option MOST CRITICAL FLOAT, it is the least of the start or finish floats.

    :-)

    Rav