P6 - Filters

Bijaya BajracharyaMember for 21 years 8 months
Created
5
20
0
It appears there is a bug in P6. Filters for resources and roles does not work when you use "equal" parameter. It works when you use "contains" parameter only.

5 replies

Oldest first
  1. 0
    Anoon Iimos ·
    Bijaya,

    try selecting the correct Resource ID
  2. 0
    Anoon Iimos ·
    it happens when you got multiple resources assigned to certain activities. If you got single resource assigned to activities, "equals" will work
  3. 0
    Waseem Saber ·
    Anoon,
    well spotted, it works if you know how to work.....

    Cheers
  4. 0
    Anoon Iimos ·
    yes, but really sometimes the filters of P6 are confusing, because there are defaults that you can’t modify, and when you try to use multiple filters on Bars..(i really had a hard time), i’m not sure though if I got the bug or it is with the software...

    note: you can modify the default filters by copying and pasting.
  5. 0
    Bijaya Bajracharya ·
    This problem has been acknowledged by Primavera and they are working on it. There is an ongoing discussion in POINT about this. I posted this just to make others to be aware of it. Nothing to do with if you know how to work!

    The problem appears that the programme is not looking at the predefined values of Role IDs or Resources.

    To illustrate the problem, create any filter, eg. Roles Id equals ..., under the Value column, you have to enter the value manually. This is strange. Since Role IDs are already defined in Enterprise/Roles, when you create a filter for it, you would expect that only those defined values should be available to choose from when creating a filter.

    If you try to filter under activity id, you can’t enter the values manually - you have to pick it up from the pull down menu. I think it should be similar while filtering for Role IDs and Resources as well. But it is not and it does not work properly.

Log in or join to reply