Multi suspend activities

Reza HasheminiaMember for 18 years 11 months
Created
1
11
0
Dear friends,
In the cases you have many suspention on an activity, is there any particular way to apply?
Thanks.

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Reza,
    In P5/P6 just one suspension is possible. You’ll have to create additional activities.
    Cheers
    Dieter