[Help] How to export external relationship to xls file
In the Open Standard
Zhang HaixiangMember for 21 years 7 months
- Created
- 1
- 11
0
hello,
I’m using P5.
I have a project(Project A rev.0)from others(.xer) and imported into my database.
then i added some activities to this project and link these activities to some other projects.
Now the problem is I received a new update of this project(project A rev.1),I want to export the activities that i added in rev.0 with relationships and then import into rev.1.So I do not need to add those activities and link again.
Can someone help me how to do this,
I tried export to xls, but found external relationship were not exported.
thanks
I’m using P5.
I have a project(Project A rev.0)from others(.xer) and imported into my database.
then i added some activities to this project and link these activities to some other projects.
Now the problem is I received a new update of this project(project A rev.1),I want to export the activities that i added in rev.0 with relationships and then import into rev.1.So I do not need to add those activities and link again.
Can someone help me how to do this,
I tried export to xls, but found external relationship were not exported.
thanks
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?