Decimals in Total Float - P6 - why?

Christopher NicolasMember for 20 years 5 months
Created
3
30
0
I have to put 2 decimal points for total float and for some reason the summary is showing for example 130.10 days total float instead of 130.00. None of the activties within the group have the 0.10 float yet the summary reads 130.10. Does anyone know why?

3 replies

Oldest first
  1. 0
    Paul Harris ·
    Have you checked the calendar finish times or activity durations, something is probably not matching.


    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  2. 0
    Christopher Nicolas ·
    Paul - none of the durations contain decimal points and the calendar is a standard 10 hour day, 6 day week. I am trying to figure it out??
  3. 0
    Terry Barber ·
    1 of your activity’s is starting or finishing at ???.10 You need to find it and i assume that you have a few activity’s that have this + 000’10 time period. You need to find the top activity that has this time period and when corrected it will cascade down through your programme and correct them all.