P6 dbase backup

Ahmed SeddikMember for 20 years 10 months
Created
5
9
0
I make dbase backup by using SQL Server Management Studio Express , when restore this backup at another pc it fail to open how can I solve this problem

5 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Ahmed,

    Did you specify the source & location of backup sets to restore? Make sure that you choose from device instead of from database.
  2. 0
    Dieter Wambach ·
    Ahmed
    I assume this is an item of the SQL-Server. Did you synchronize Privuser and pubuser? Without synchronization SQL-Server doesn’t accept restored data from different servers.
    Regards
    Dieter
  3. 0
    Ahmed Seddik ·
    I need to use the backup at another server
  4. 0
    Duy Huynh ·
    Verify the following after you restored the db into the new server (login to MS SQL management studio first):
    - Are there ’privuser’ and ’pubuser’ created as log in name for the server (under: /Security/Logins)? If no create this two.

    - Next, after the two users above available, make a "New Query" like below:

    exec sp_change_users_login ’Update_One’,’privuser’,’privuser’
    exec sp_change_users_login ’Update_One’,’pubuser’,’pubuser’
    go

    This will update privuser and pubuser of the server into the database.

    Hope this help
  5. 0
    Duy Huynh ·
    Sorry, before that two lines in the query, you need to specify:

    use [pmdb$primavera] -- change it to your actual P6 database name as needed.

Log in or join to reply