Status Issue in P5!
In the Open Standard
Mohsen MMember for 18 years 8 months
- Created
- 3
- 14
0
Hi,
Every week that I status my programme the remaining works bars will become same as the target bars for many activities. For example, I have an activity with actual start on 8 Sep 08, the status date is 21 Nov 08 and it will be finished on 18 Dec 08. The target bar for this activity is 20 Jan 09. Now, if I status the programme to 28 Nov 08 the remaining work will be planned to finish on 20 Jan 09. Same issue with many other activities in the programme??
Regards,
Mohsen
Every week that I status my programme the remaining works bars will become same as the target bars for many activities. For example, I have an activity with actual start on 8 Sep 08, the status date is 21 Nov 08 and it will be finished on 18 Dec 08. The target bar for this activity is 20 Jan 09. Now, if I status the programme to 28 Nov 08 the remaining work will be planned to finish on 20 Jan 09. Same issue with many other activities in the programme??
Regards,
Mohsen
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?