Primavera Digger

Anu TorMember for 19 years 8 months
Created
1
18
0
Good morning,

Anybody know the best compare software to P3 between original sch. and updating one ane. Where can I find and dowload?

Thank you,

1 reply

Oldest first
  1. 0
    Ronald Winter ·
    For comparison of P3 schedule updates, you have two choices; Claim Digger (sold my Primavera) and Schedule Analyzer (sold by my company, Ron Winter Consulting LLC.)

    A fact sheet on Claim Digger may be found on the Primavera website at https://www.primavera.com/files/datasheet/claim_digger_datasheet.pdf but for the life of me, I cannot find anywhere on the Primavera.com website that says it is still for sale. I wonder if this is Oracle’s way of saying, "Hellow"?

    The Schedule Analyzer main page is at www.ScheduleAnalyzer.com. Schedule Analyzer is too large to download, but overseas mail is an option.