Displaying Lag Column in Activity Table

Ijaz AhmadMember for 20 years 4 months
Created
2
21
0
Hi Guys,
Can somebody tell me how to display the "Lag" Column in the activity table. I am not finding the lag column in the columns list.
Thanks
Ijaz

2 replies

Oldest first
  1. 0
    Arend Kok ·
    Hi Ijaz.

    You will find the lag column in you relationships or your predecessor and successors tabs. You cannot show this per activity as lag is defined per relationship, and one activity can have multiple relationships.

    Hope this makes sense.

  2. 0
    Arnold Puy ·
    Hi Ijaz,

    You cannot show the lag in the Activities Column Workspace. The only workaround is to go to Report Directory and create & modify report using activity relationship as subject area and send report to ASCII text file .csv

    Regards,

    Arnold