Customizing title block

Ferdinand Fincalero, PMPMember for 18 years 3 months
Created
2
16
0
Dear Planners,

Any idea on how to customize the default double spacing of text rows in the title block (header/footer) into single spacing?

Thanks.

2 replies

Oldest first
  1. 0
    Mark M ·
    Hi Ferdinand

    See the following thread;
    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=60999

    Posted by Michael Ridino;

    "Use Shift enter to move text a single line down, pressing enter by itself does a double space"

    Regards
    Mark
  2. 0
    Ferdinand Fincalero, PMP ·
    Thank you so much Mark.

    Cheers!