Confusion in Must Finish by date in P6
In the Open Standard
Haresh JayanthMember for 20 years 2 months
- Created
- 7
- 35
0
Dear Rodel,
When i keep Must Finish by date of my project by 24th July 2011 time 7:00pm , Primavera is showing my completion date of my project as 25th July 2011 with Zero total float?? How is it possible....
I have used a Level of effort activity called Project Duration. Project duration activity" is linked to start-start with "first activity of the Project i.e. Project start date and finish to finish with last activity of the project i.e. Project Finish date....it is showing the entire Project Duration..Now this level of effort activity is showing completion as 25th July 2010 10:00 am....
And also if i change my Must finish date time to 24th July 2011 , 1:00 pm , then Primavera now shows project finish date as 24th July 2011....
So kindly explain me why primavera takes project completion as 25th July 2011 , when i set my Must finish by date as 24th July 2011 , 7:00 pm.
regards,
Haresh
When i keep Must Finish by date of my project by 24th July 2011 time 7:00pm , Primavera is showing my completion date of my project as 25th July 2011 with Zero total float?? How is it possible....
I have used a Level of effort activity called Project Duration. Project duration activity" is linked to start-start with "first activity of the Project i.e. Project start date and finish to finish with last activity of the project i.e. Project Finish date....it is showing the entire Project Duration..Now this level of effort activity is showing completion as 25th July 2010 10:00 am....
And also if i change my Must finish date time to 24th July 2011 , 1:00 pm , then Primavera now shows project finish date as 24th July 2011....
So kindly explain me why primavera takes project completion as 25th July 2011 , when i set my Must finish by date as 24th July 2011 , 7:00 pm.
regards,
Haresh
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?