Show number of resoures in activity column

Vaughn EdwardsMember for 18 years 6 months
Created
6
44
0
I have looked everywhere to create a column in P6 to show the number of resources assigned to an activity. I know P3 used units of time to show this, but can’t find what to use in P6. Can this be done???

6 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Vaugh,
    It is now on Resource Window (P3 don’t have before) and called Budgeted Unit/Time for Budget units and Remaining Unit/Time for Remaining Unit. It is also available on Activity Window Detail-> Resource tab.
  2. 0
    Vaughn Edwards ·
    Thanks for your reply. I have found the number of resources under the resource and activity windows, but the budgeted Unit/Time isn’t available to choose to inset a column. Thats my problem.
  3. 0
    Roger Booth ·
    I use one of the user defined fields and then attach that UDF to the bar. Gives you a display very similar to dare I say Microsoft Project
  4. 0
    Rodel Marasigan ·
    Vaughn,
    If using Resource Window, right click and select columns-> Customize.
    Under General you can select Budget Unit/Time and Remaining Unit/Time.

    If using Activity Window select Resources tab. Right click on Resources table and select Customize Resource Columns. Under General select Budget Unit/Time and Remaining Unit/Time.
  5. 0
    Vaughn Edwards ·
    I understand how to get Budgeted Unit/Time to appear in the Activity and Resource windows, what I’m looking to do is see a column in the Gantt view of the number of resources assigned to that activity.
  6. 0
    Rodel Marasigan ·
    Vaughn,
    Sorry for misunderstanding as you mentioned columns and not label. If label you wanted as per Roger advise use UDF and populate using Global Change then assigned to a bar. You can always run Global Change to update if resources change.

    Hope this help.